Mumby 48 Build Progress for October 2024

Progress for October 2024 looks good even though we lost almost a week due to Cambodia public holidays (around a full month of public holidays per year). As this is our first Mumby we have lofted topside plate and flare plates onto plywood to ensure that we have a 100% fit before cutting the 4mm plate. This is fairly time consuming work but necessary when cnc cut parts are not supplied. We managed to get the inner topside and flare plate fitted and tacked plus template for outer topsides lofted and cut.

Forward partitions are installed per client requirement, one dry sail locker and one for the wet sails.

Mast support view

Mast support fabricated and tacked in, forward stiffener plates fabricated and installed.

Forward stiffener plate

The keels and underfloor supports have now been fully welded.